Detail Engineering Design and Construction supervision of Disaster preparedness and response for safe drinking water supply in the Kathmandu Valley(UNICEF Finance)

 

Project Description

Disaster preparedness and response plan for safe drinking water in the Kathmandu Valley consisted of up-gradation of deep tube-wells and make them ready for emergency operation with generator back ups, fuels and storage systems.

 

The up-gradation and improvements were done for KUKL – Jwagal, UN Park, KUKL – Balkumari, IOE – Pulchowk Campus, NARC – Khumaltar and Department of Irrigation – Jawalakhel. The project activities consisted of:

·           Earthquake resistant buildings

·           Supply and installation of Generators for deep-tube well pumps

·           Sanitation development at project sites

·           Site development works

·           Up-gradation of deep-tube well and submersible pumps and booster pumps

·           Electric works and generator installations

·           Pumping main pipes and pipe line installation

·           Water treatment plant of 30m3/hr capacity

·           Water reservoir tanks

·           Rainwater harvesting system etc.

·           Earthquake resistant buildings

·           Supply and installation of Generators for deep-tube well pumps

·           Sanitation development at project sites

·           Site development works

·           Up-gradation of deep-tube well and submersible pumps and booster pumps

·           Electric works and generator installations

·           Pumping main pipes and pipe line installation

·           Water treatment plant of 30m3/hr capacity

·           Water reservoir tanks

·           Rainwater harvesting system etc.

--> ·         concept designs and detail designs,

·         preparation of working drawings,

·         BOQ. Estimate and tender documents,

·         tender evaluations,

·         preparation of operation and maintenance manuals and training of technicians for capacity building and human resource development,

·         full time site supervision,

·         checking of running and final bills,

·         claim settlements,

final documents for handover etc.

-->