Rehabilitation , Extension and Development of Water Supply Project:
Detailed Survey of 442.418 Km of new and old Transmission and Distribution Line and Design of 106 lps Total Water Demand, 5 number of Reservoir capacity 30000 cu.m, 900 cu.m, 600cu.m, 500 Cu.m, 500 Cu.m), 3 Number of Sump Well (200 cu.m,50cu.m,50cu.m); 3 nos. of Booster stations for Pumping, 2 number of Intake Rehabilitation and protection works, Plantation works, Water Treatment Facilities – Flocculator and sedimentation tank , Rapid sand filter, Backwash Reservoir – 16.2 MLD Capacity; Total tap connection – 40732 numbers; Design Year Population – 1,85,486; FIRR – 4.79%, EIRR – 65.52%, AIEC – 48.91, AIFC – 34.66; Generator 4 numbers – 150 kv, Transformers – 4 number 11 kv – 10 km, Protection of Sardu Watershed, Road Reinstatements works 172Km , River crossing works, New Tube well Drilling works, Pressure Test/ Leakage tests, NRW assessment, GIS Mapping of Dharan Muinicipality, GESI training, Environmental Mitigation works, Operation by contractor for 9 month, Community development and GESI Activity programmes, Formation of Dharan Water Supply Management Board, Preparation of Business Plan ,Asset evaluation of NWSC, Preparation of By-Laws.